Aims to study the effect of fluctuations caused by clouds on the voltage quality with the possible reasons of the PV system connected to the low voltage distribution grid in Algiers.
Figure 5. shows the daily voltage on the three phases of the PV system. These days were chosen because most of the out-of-range voltages occurred during this period (effect of radiation and clouds), and the different scenarios of the loads at PCC on each phase versus the days of operation of the 23, 24, 25 26, and 29 April 2021 (working days in the laboratory), and the days without use of loads corresponding to the weekend on April 27 and 28, 2021.
A comparison between the daily voltage profiles of the three single-phase phases during the seven days of testing shows that the voltage decreases during the hours of PV production and peak load usage at the PCC between 8:00 am and 5:00 pm, where, the voltage varies between the three phases according to the loads connected. The maximum voltage variation is seen during the five working days, from Sunday to Thursday, compared to the two weekend days.
Figure 6. to Fig. 8. illustrate the active power produced by the PV system, the Pst and the Plt flicker indices of the three PV systems, respectively.
A significant correlation was shown between the active power and the flicker indices. However, a slight effect of PV systems on the flicker level during the hours of PV production with fluctuations in power produced by the PV system is observed, due to the absence of the clouds during those days. However, the low impedances and loads connected at the PCC make the Pst and the Plt flickers very significant. The values are initialized from different initial values that dependent on the connection impedance of each phase, loads connected at PCCs, and the THD of the network at PCC.
Figure 6. is showing the variations of the Pst and the Plt for the first PV subsystem, with respect to the power produced vary between 0.5 and 2 in the most of the time, due to the load fluctuation. In addition, a slight effect of the fluctuating power due to the clouds passing over the system compared to the very high Pst level observed in the duration of the PV production. The Plt level during the entire measurement period is greater than one, and a slight effect of the PV production on the Plt level is observed.
Figure 7. is showing the Pst level of the second PV subsystem varies between 0.4 and 1.6, where these values started at an initial value of 0.4, that represents the Pst of the network, which depends on the connection impedance of this phase and the load connected at the PCC. The effect of PV production is well observed; where the Pst level follows the active power variation. The same effect is observed for the Plt, whose range of variation is 0.4 to 1.2 at low cost.
For the third PV subsystem (Fig. 8.), the level of the initial Pst is low compared to the other PV subsystems from which it starts at an initial value of 0.2, and the same for the calculated Plt from which it increases by a value of 0.2 up to 1.
4.1 Impact of PV System Penetration on Pst and Plt flicker indices
A case study is performed to investigate the severity of the flicker caused by varying PV penetration levels of the three PV systems when the power grid is used as a power source. This study is carried out for two selected days. In order to reveal the penetration effect of PV production in the three subsystems, the first day is a reference day of April 27, 2021, which represents a weekend, is considered as a reference day where, the effect network and loads at the PCC can be neglected. The second day of April 24, 2021, is selected to reveal the the Pst and Plt flicker indices variations caused by the PV system with the presence of the loads connected to the PCC.
Figure 9. illustrates interaction impact between the network and the power penetration of the PV system on the Pst and Plt indices of the first subsystem. As can be seen that for the reference day when the PV system is not connected to the grid (0% of the production capacity), the flicker indices Pst and Plt are respectively 1.28 and 1.05. These values represent the flicker indices of the loads connected to the PCC which exceed the normalized values (see table). The variations of these indices at PCC may depend on the impedance connection between the PV system and the grid, in addition to the loads connected and the problems of harmonics on this phase. When the PV production penetration increases from 25%, 50% and from the maximum capacity the Pst vary respectively 1.28, 1.3,1.3, and the Plt vary respectively (1.05,1.07,1.13,1.15). During the second day the flicker at the PCC is combined with the flickers introduced by the power fluctuations and solar radiation. It is also observed that the Pst indices become almost the same values as on the reference day, due to the very high indices levels of the indices produced by the loads and the grid at the PCC for all the PV power levels where the Pst varies respectively (1.28, 1.3,1.3,1.98), and the Plt vary respectively (1.05,1.16,1.26,1.54)
Figure 10. illustrates the indices Pst and Plt of the second PV subsystem. When the PV subsystem is not connected to the grid during the two days, the Pst and Plt are respectively 0.5 and 0.44. For the reference day, the results show a significant increase in Pst and Plt on the second phase, when the PV capacity gradually increases from 25% to the maximum production capacity. Pst increases from 0.55 to 0.58 for 50% of the capacity, and from 0.78 for the maximum capacity. Plt increases from 0.49 to 0.51 for 50% of production, and 0.7 for maximum capacity. For the second day we can observe a slight effect of the power fluctuations in the indices levels or these indices increase compared to the penetration level of the PV system, and the activities of this phase, otherwise the values of the flicker indices in short and long term are respectively (0,5,0.92, 1.18,1.18) and (0.44,0.82,0.94,0.92).
For the third PV subsystem, the effect of fluctuations appears when the effect of the dominance of the loads and the grid are weak; Fig. 11. shows that the Pst and the Plt are respectively 0.3 and 0.29 when the PV system is not connected to the grid for the two days. A significant increase in Pst and Plt on the third phase, when the PV capacity gradually increases from 25% to the maximum production capacity. Pst goes from 0.36 to 0.37 for 50% of the capacity, and from 0.55 for the maximum capacity. Plt increases from 0.35 to 0.36 for 50% of production, and 0.52 for maximum capacity. For the second day we can observe that the power fluctuations effect on the indices levels, these indices increase compared to the level of penetration of the PV system, and the activities on this phase. The values of the short and long flicker indices term are respectively (0.3,0.36, 0.46,1.34) and (0.29,0.33,0.36,0.81). In this phase, the effect of loads and the network are weak but the effect of power fluctuations is also weak and has no significant impact on the flicker indices.
4.2 Impact of Second Order Current Harmonic Rate
Harmonic currents are due to the presence of non-linear electrical loads at the PCC. The circulation current is greater than the arm current of the non-linear loads static converters is dominated by the second order harmonic. the second harmonic current causes fluctuations voltage on the load capacitor at the connection point between the load, the PV system, and the grid. These fluctuations depend on the number of non-linear loads connected and the impedance of each phase, otherwise these voltage fluctuations affects the level of flickers at the integration point. Figure 12. shows the variation of the second order harmonics on each phase in the test period where the harmonics effect appears in three phases with different values except the photovoltaic production period resulting from the loads connected in each phase
4.3 Impact variations in radiation on waveform and voltage quality
In order to assess the relationship between the flicker indices and the current waveform which directly depends on the solar radiations, the analysis is carried out on three typical weather conditions: an overcast day (April 24, 2021), a cloudy day (April 26, 2021) and a sunny day (April 28, 2021). Figure 13, Fig. 14, Fig. 15, and Fig. 16 show the current, voltage fluctuations, and flicker indices during the three weather scenarios. According to the results there is some correlation between the weather conditions. flicker level, and voltage waveform
According to Fig. 13, the variations in voltage observed mainly depend on solar radiation and the current produced by the photovoltaic system, Fig. 14 and Fig. 15 show the short-term and long-term flicker propagation during a cloudy day, a rainy day, and a sunny day, respectively. The flicker emission during the cloudy day is higher than the emission. Offlickerin during a sunny day and a day with overcast sky
4.4 Impact of the Power Ramp Rate On The Voltage Variations
Figure 17. is showing the voltage ramp is linked to changes in radiation and the cloud passage, otherwise the quality of the energevent versus the power ramp event for the three PV subsystems at the PCC. To find out the impact of the power ramp according to the solar radiation ramp event on the voltage quality, we applied the two models (3) and (4) by a resolution with an accuracy of 5 min. In contrast, the results showed that voltage fluctuations in the three subsystems are produced at the output of the inverters.The results confirm that the two models give different results, furthermore the second model shows the clouds effect as the first takes into account the effect of connected loads which are related to the number and load type, voltage variations do not exceed 4% according to model (03) for the three PV subsystems, in contrast and according to the second model (04) the voltage variations 10% for the first subsystem, 9% for the second sub -system, and 7% for the third.
4.5 Impact the location of the PV system
The powers at the output of the PV system, at the PCC and the powers of the loads for a period on March 11, 2020 are shown in Fig. 18. When many fluctuations in radiation were observed. To show the relationship between the power fluctuation caused by the fluctuations in solar radiation at the output of PV inverters and at PCC at the level of THDi and THDv. Table 5shows the total THDi and THDv for different power ramps on the three locations (inverter, PCC, load). According to the results, the THDi is very sensitive to changes in the power ramp and varies depending on the location of the integration of the PV system in the grid and with respect to the load types connected to the PCC. The THDi has an almost inverse relationship with the actual inverter output power, which in turn affects the level of THDi at the PCC. On the other hand, the total voltage THDv is not sensitive by changes in solar radiation but it is sensitive to the loads type connected.
Table 5 Total THDi and THDv for different PV capacity production
Case
|
PPV
|
PPCC
|
P Load
|
PV Penetration
|
THD i
|
THD v
|
W
|
%
|
PV
|
PCC
|
Load
|
PV
|
PCC
|
load
|
% f
|
% f
|
% f
|
%f
|
% f
|
% f
|
01
|
2623
|
2309
|
336.3
|
87.43
|
5.3
|
11.2
|
37.9
|
6.4
|
6.4
|
6.4
|
02
|
1884
|
1566
|
334.9
|
62.8
|
9
|
30.3
|
37.6
|
6.4
|
6.4
|
6.4
|
03
|
307.6
|
-32.1
|
334.4
|
10.25
|
24
|
95.6
|
39.3
|
6.5
|
6.5
|
6.5
|
04
|
292.7
|
-50.4
|
334.9
|
9.75
|
24.9
|
95.7
|
41.4
|
6.5
|
6.6
|
6.5
|
05
|
425.4
|
92.7
|
335.7
|
14.18
|
20
|
92
|
43.2
|
6.6
|
6.6
|
6.6
|
06
|
696.3
|
367.8
|
336.6
|
23.21
|
15.3
|
67.7
|
43.3
|
6.6
|
6.6
|
6.6
|
07
|
2263
|
1947
|
336.8
|
75.43
|
6.4
|
16.7
|
41.3
|
6.5
|
6.5
|
6.5
|
08
|
2698
|
2385
|
336
|
89.93
|
5.2
|
11.1
|
38.8
|
6.4
|
6.4
|
6.4
|
09
|
2189
|
1871
|
336.7
|
72.96
|
7.2
|
21.7
|
40.8
|
6.5
|
6.5
|
6.5
|
10
|
2399
|
2083
|
337.7
|
79.96
|
5.7
|
13.5
|
42.6
|
6.5
|
6.5
|
6.5
|
11
|
2462
|
2146
|
337.6
|
82.06
|
5.5
|
12.8
|
42.6
|
6.4
|
6.4
|
6.4
|
12
|
2450
|
2135
|
337.2
|
81.66
|
5.5
|
12.7
|
42.2
|
6.4
|
6.4
|
6.4
|
13
|
2472
|
2159
|
336.8
|
82.4
|
5.4
|
12.4
|
41.9
|
6.4
|
6.4
|
6.4
|