In the simulations, discharge values with return periods of 500 and 1000 years (Q500 and Q1000) for a 20-hour hydrograph were used. The following 4 cases were modelled:
Case 1: Before rehabilitation of Ismetiye creek with Q500.
Case 2: Before rehabilitation of Ismetiye creek with Q1000.
Case 3: After rehabilitation of Ismetiye creek with Q500.
Case 4: After rehabilitation of Ismetiye creek with Q1000.
3.1. Results of 2D Simulation Before Rehabilitation of Ismetiye Creek
There was a significant flooding throughout the catchment area of Ismetiye creek as shown in Fig 9. In the case of Q500, the time of maximum extent is 7 hours 12 minutes and the maximum depth is 5.0 m, also shown in Fig 9.
Before rehabilitation, the extent of flooding was more at the beginning of the channel. As we go downstream, there was overbank flow observed which resulted in the flooding of catchment area. The overbank flow also flooded the dry channel present in the south of the Ismetiye creek. Moreover, new settlement region located on the right overbank side of downstream end of the channel also observed flooding.
3.2. Results of 2D Simulation After Rehabilitation of Ismetiye Creek
In the case of simulation after rehabilitation of Ismetiye Creek, it was found that flooding decreased significantly as compared to the case of natural channel. Fig 10. shows the flood maps after rehabilitation for Q500 and Q1000 respectively. For Q500, the time of maximum extent is 7 hour 52 minutes and the maximum depth is 5.544 m. For Q1000, the time of maximum extent is 7 hour 52 minutes and the maximum depth is 5.794 m.
After rehabilitation, there was more flow inside the main channel and less on the overbanks. The new settlements in the downstream were not inundated at all. Also, the channel in south of Ismetiye creek was not flooded at all.
As expected, the extent of flooding observed for Q1000 was more than that of Q500. The maximum depth observed in case of Q1000 was also higher as compared to that of Q500. Before rehabilitation, maximum depth for Q500 was 5.0 m while for Q1000, it was 5.12 m. On the other hand, after rehabilitation, maximum depth in case of Q500 was 5.544 m while for Q1000, it was 5.794 m. Clearly, the maximum depths were higher after rehabilitation because of the fact that more water was retained in the main channel.
Fig 11 shows the comparison of velocity maps for Q500 before and after rehabilitation of Ismetiye creek.
In case of Q500 before rehabilitation, a maximum velocity of 4.44 m/s was observed at X= 2500 m in the main channel. High velocity of flow in a natural river bed would result in erosion of soil and deformation of the bed. After rehabilitation, a maximum velocity of 13.7 m/s at X=75 m was observed in the main channel. Thus, the velocity of flow in the main channel was much less before rehabilitation as compared to the case of after rehabilitation. This was observed due to the fact that the main channel before rehabilitation retained less water with high overflow. However, for the overbanks, velocity was observed to be higher before rehabilitation and lower after rehabilitation. This can also be attributed to the fact that there was high overflow before rehabilitation. Hence, it can be said that not only did the rehabilitation of channel decrease the overflow but also the decrease in velocity of overflow after rehabilitation reduced the risk of soil erosion near the banks.
For Q1000, maximum velocity of 4.47 m/s was observed at X= 2500 m in the main channel before rehabilitation. After rehabilitation, a maximum velocity of 14.8 m/s was observed at X= 75 m. As compared to the maximum velocities obtained in the case of Q500, the maximum velocities in the case of Q1000 were marginally higher. However, the locations of points of maximum velocities remained the same as that of Q500.
Flood hazard maps were created to compare the risk of floods before and after the rehabilitation of Ismetiye creek. Flood risk zones as per the guidelines of Federal Emergency Management Agency (FEMA) 2018 were defined as shown in Table 2. The magnitude of flood hazard is calculated by Eq. (3) (FEMA 2018).
Table 2. Flood risk classification scheme (modified from FEMA 2018)
Hazard (m2/s)
|
Flood Risk
|
Hazard Rating
|
< 0.2
|
Very Low
|
0
|
0.2-0.5
|
Low
|
1
|
0.5-1.0
|
Moderate
|
2
|
1.0-2.0
|
High
|
3
|
> 2.0
|
Extreme
|
4
|
Hazard zones were assigned a hazard rating starting from 0 to 4 with 0 corresponding to very low risk zone and 4 corresponding to extreme risk zone. Fig 12 shows the comparison of flood hazard zones before and after rehabilitation of Ismetiye creek for Q500 and Q1000.
From the hazard maps of natural channel and rehabilitated channel, it was observed that hazard rating was maximum inside the main channel taking the values 3 (high risk) and 4 (extreme risk) along the channel path.
The catchment area in case of natural channel was more prone to flooding as expected and the extent of hazard was more. On the right overbank side, there were traces of yellow, blue and red colors which correspond to a hazard rating of 1,2 and 3 respectively. The regions on right overbank side of Ismetiye with hazard rating of 2 (blue) and 3 (red) are in the vicinity of inhabited areas, making those areas susceptible to the danger of flooding.
However, after rehabilitation, the extent of hazard considerably decreased and a hazard map with green (hazard rating = 0) was observed throughout the catchment area except for the main channel and its immediate surroundings where some spots with yellow (hazard rating = 1) and blue (hazard rating = 2) were observed. However, these spots lie in uninhabited regions.
As expected, the extent of flood hazard was more in case of Q1000 as compared to that of Q500. Due to high velocity of flow in case of rehabilitated channel, flood hazard was more near the banks as compared to the case of natural channel. Before rehabilitation, new settlements towards right over bank side of the downstream end of Ismetiye channel were exposed to inundations. However, there is no flooding seen in these areas after rehabilitation of the channel.
Cross-sectional lines were drawn at X= 75 m, 1500 m, 3000 m and 4000 m along the channel in order to obtain flow hydrographs for Q500 and Q1000. Separate lines were drawn for the main channel (MC) and each overbank. Therefore, hydrographs for the MC, right overbank (ROB) and left overbank (LOB) were calculated separately for each cross-section. Fig 13 shows the cross-sections at X= 75 m and X=1500 m for Q1000.
Flow hydrographs for X=75 m and X =1500 m at Q=500 m3/s and Q=1000 m3/s are depicted by Fig 14.
Fig 15. shows the cross-sections at X= 3000 m and X=4000 m for Q1000.
Flow hydrographs for X=3000 m and X = 4000 m at Q=500 m3/s and Q=1000 m3/s are depicted by Fig 16.
The peak in MC before rehabilitation was attained at 84.19 m3/s and after rehabilitation, it was attained at 168.6 m3/s. At X=4000 m, before rehabilitation, it was also observed that flow hydrograph peak was constant after a certain point. This indicated that maximum flow capacity of natural channel was reached. Table 3 and Table 4 show the peak discharge values for main channel and overbanks.
Table 3. Peak discharge values for natural and concrete channels in case of Q500
|
Natural Channel
|
Concrete Channel
|
X
(m)
|
QMC (m3/s)
|
QROB (m3/s)
|
QLOB (m3/s)
|
QMC
(m3/s)
|
QROB
(m3/s)
|
QLOB
(m3/s)
|
75
|
91.27
|
25.81
|
26.45
|
143.65
|
0
|
0
|
1500
|
101.35
|
20.21
|
5.27
|
143.17
|
0
|
0
|
3000
|
83.9
|
50.84
|
6.24
|
143.6
|
0
|
0
|
4000
|
82.93
|
50.71
|
4.82
|
143.7
|
0
|
0
|
Table 4. Peak discharge values for natural and concrete channels in case of Q1000
|
Natural Channel
|
Concrete Channel
|
X
(m)
|
QMC
(m3/s)
|
QROB
(m3/s)
|
QLOB
(m3/s)
|
QMC
(m3/s)
|
QROB
(m3/s)
|
QLOB
(m3/s)
|
75
|
104.58
|
29.86
|
31.36
|
168.42
|
0
|
0
|
1500
|
110.53
|
23.77
|
6.64
|
168.14
|
0
|
0
|
3000
|
85.5
|
73.29
|
8.44
|
168.3
|
0
|
0
|
4000
|
84.19
|
73.45
|
6.91
|
168.6
|
0
|
0
|
Here is a generalization of results that can be concluded from the above graphs valid for both Q500 and Q1000:
- It is obvious from the graphs that flow in main channel was more for rehabilitated case as compared to the natural case. This is because of the fact that channel capacity increased. The erosion of banks and deposition of sediments lowered the channel capacity in natural river. This resulted in higher peaks of hydrographs at the shown sections across the main channel after rehabilitation.
- On the other hand, before rehabilitation, due to high overflow in the main channel, the peaks of flow hydrographs were comparatively lower.
- Likewise, for the overbanks, the flooding was more in case of natural channel as compared to the rehabilitated channel which is also reflected by higher peaks of flow hydrographs.
These results clearly indicate that the rehabilitation work of Ismetiye creek confined most of the flooding to the main channel preventing the overbanks from risk of inundation. Thus, it is safe to say that rehabilitation work on a channel in its natural state makes the catchment areas of the channel less prone to the risk of flooding.