The vertical bearing capacity of friction-type pile foundation is provided by the side friction resistance and the end friction resistance of the pile. Under the vertical load, the soil around the pile exerts its side friction resistance from top to bottom. The development of side friction resistance is related to the nature of the soil around the pile and the load on the top of the pile. The axial force of the vertical compressed pile body decreases gradually from top to bottom along the pile body. The reduction of axial force of pile body is due to the exertion of friction resistance on the side of the pile. The soil around the pile with higher friction resistance will change the axial force of the corresponding pile body greatly. After the friction resistance along the side of the pile body has been fully exerted, the axial force transmitted to the bottom of the pile is borne by the bearing layer soil at the end of the pile. Finally, the force of the pile body is balanced by the coordination of the friction resistance at the side of the pile and the friction resistance at the end of the pile. Therefore, the vertical bearing capacity of the pile is equal to the sum of the side friction resistance and the end friction resistance of the pile. As a result, the variation rule of pile side friction resistance can be reflected by the distribution of axial force (stress) of pile body. The relationship between axial force of pile body and side friction resistance is shown in Figure 7.
A large number of studies show that in pile group foundation, each foundation pile bears different loads transmitted from the bearing platform plate, and the soil around the foundation pile at different positions also has different effects on the pile, so it is difficult to compare and analyze them. In this section, the foundation pile ZZ1 at a specific location is selected for the analysis of the vertical bearing characteristics of the pile during vibration. To facilitate analysis, the cumulative coefficient of pile side friction resistance CCPF is introduced in this paper.
The pile is divided into n sections, Ni+1 and Ni are the axial forces at section i and i+1 of the pile body respectively, and P foundation represents the sum of the side friction resistance of the pile under equivalent load Q. P0=Q-Nmin,9 pile is adopted in the model, so Q takes 1/9 of the load on the bearing cap and Nmin is the axial force at the bottom of the pile (considered as the resistance at the end of the pile).
The number of CCPF reflects the distribution of soil friction around the pile along the side of the pile, the change of CCPF reflects the change of side friction resistance. In liquefied sites, liquefaction of the soil layer under horizontal seismic forces will lead to a decrease in shear strength of the soil, which will naturally reduce the friction on the side of the pile provided. The axial force of pile body will inevitably change with the change of pile side friction. Such change trend and law can be reflected in the change of cumulative coefficient of pile side friction.
5.1 CCPF distribution law and characteristics of single pile system along the pile body
Firstly, single pile system is selected as the research object. By analyzing the distribution rule and characteristics of CCPF along the pile body, the change of vertical bearing capacity of single pile during earthquake is further analyzed to verify whether CCPF can reflect the common action mechanism of pile and soil comprehensively and reasonably. Vibration time points are 0s, 15s, 25s and 35s. Pile stress is picked up every 5cm along the pile body. According to the stress, the axial force can be obtained, and then the side friction resistance of each section of soil around the pile can be obtained. In the laboratory test, 750N load is applied before vibration of pile group foundation of 9 piles. Therefore, 1/9 of pile group, i.e. 83.33N, is applied to single pile. From the model calculation, the stress of the pile body is obtained directly, and then the curve of CCPF along the pile body at different specific moment of earthquake action is obtained by further calculation. See Fig. 8, the corresponding changing values are shown in Table 5. In addition, for the purpose of analysis, static load tests are carried out on the pile-soil system at different times of vibration, and the corresponding Q-S curve is obtained as shown in Fig. 9, the relevant values are shown in Table 6.
Table 5
The changing values of the CCPF at different positions of pile during shaking
shaking time(s)
|
Longitudinal depth of pile(cm)
|
0
|
-5
|
-10
|
-15
|
-20
|
-25
|
-30
|
-35
|
-40
|
-45
|
-50
|
-55
|
-60
|
0
|
0
|
5
|
11
|
17
|
28
|
39
|
49
|
61
|
70
|
79
|
85
|
93
|
100
|
15
|
0
|
0
|
1
|
6
|
12
|
18
|
27
|
36
|
54
|
70
|
81
|
91
|
98
|
25
|
0
|
0
|
0
|
1
|
2
|
4
|
9
|
16
|
28
|
37
|
59
|
75
|
90
|
35
|
0
|
0
|
0
|
0
|
1
|
2
|
3
|
5
|
10
|
21
|
32
|
51
|
75
|
Table 6
Relationship between vertical force and settlement of single pile at different specific shaking times
shaking time(s)
|
Vertical force(N)
|
80
|
100
|
120
|
140
|
160
|
180
|
200
|
220
|
240
|
260
|
280
|
300
|
0
|
0
|
-0.7
|
-1.4
|
-1.9
|
-2.6
|
-3.9
|
-6.2
|
-8.4
|
-12.3
|
-22.1
|
-37
|
-48.2
|
15
|
-1.3
|
-3.8
|
-6.2
|
-9.1
|
-12.7
|
-17.8
|
-21.9
|
-35
|
-46
|
----
|
----
|
----
|
25
|
-2.2
|
-6.7
|
-11.4
|
-16.3
|
-24.1
|
-35
|
-47
|
----
|
----
|
----
|
----
|
----
|
35
|
-3.5
|
-10.4
|
-18.1
|
-29.8
|
-39.1
|
----
|
----
|
----
|
----
|
----
|
----
|
----
|
As can be seen from Fig. 8, with the duration of vibration, the CCPF increases rapidly at the same vibration time within the range of 0 ~ − 40cm along the pile, but the longer the vibration time, the CCPF of the same pile decreases significantly. In the range of -40~-60, at 0s and 15s, CCPF maintains the same growth rate as at 0~-40cm, but at 25s and 35s, the growth rate of CCPF significantly slows down. Moreover, it can be seen that the CCPF at the bottom of the pile is reduced from 100–74% at 0s. Based on the analysis of Fig. 9, it can be seen from the Q-S curve that the curve steepens and the ultimate bearing capacity gradually decreases with the duration of vibration. The ultimate bearing capacity of single pile is about 220N at 0s, 150N at 15s and 120N at 25s. The curve drops sharply at the beginning of 35S and the bearing capacity is lower. Combined with the CCPF and Q-S curves, it can be shown that when the vibration time is short (within 15s), the soil has not been liquefied and the CCPF = 1 at the bottom of the pile indicates that the actual load acting on the top of the pile in a short time is equal to the applied load. As the time of vibration increases continuously, the soil around the pile begins to liquefy from top to bottom. The liquefied soil layer not only reduces the friction resistance on the side of the pile, but also finds that the actual load acting on the top of the pile is less than the load applied on the top of the pile. Thus, the phenomenon that CCPF at the bottom of pile is less than 1 at 25s and 35S appears.
The above analysis shows that CCPF can more intuitively reflect the distribution rule of accumulated pile side friction resistance along the pile body during earthquake. By comparing the value of CCPF at the bottom of pile with that of 1, the change of actual load on the top of pile during vibration can be clearly analyzed.
5.2 Distribution regularity and characteristics of CCPF along pile body of pile group system
The same analysis is carried out for piles in group piles foundation by means of CCPF. When the spacing between piles is 3D, 3.5D, 4D, 5D and 6D respectively, the CCPF curve of ZZ1 piles at different times of seismic action is shown in Fig. 10. The relationship between vertical force and settlement of 3D, 3.5D, 4D, 5D and 6D working conditions at different specific shaking times are shown in Table7, Table8, Table9, Table10, Table11.
Table 7
The CCPF value of the ZZ1 during shaking at the specific shaking times under 3D working condition
shaking time(s)
|
Longitudinal depth of pile(cm)
|
0
|
-5
|
-10
|
-15
|
-20
|
-25
|
-30
|
-35
|
-40
|
-45
|
-50
|
-55
|
-60
|
0
|
0
|
5
|
8
|
13
|
18
|
24
|
29
|
35
|
41
|
52
|
60
|
67
|
75
|
15
|
0
|
4
|
6
|
9
|
13
|
18
|
23
|
30
|
40
|
51
|
63
|
75
|
86
|
25
|
0
|
2
|
4
|
5
|
7
|
10
|
14
|
20
|
34
|
52
|
71
|
85
|
100
|
35
|
0
|
0
|
1
|
3
|
6
|
9
|
10
|
14
|
26
|
40
|
62
|
86
|
118
|
Table 8
The CCPF value of the ZZ1 during shaking at the specific shaking times under 3.5D working condition
shaking time(s)
|
Longitudinal depth of pile(cm)
|
0
|
-5
|
-10
|
-15
|
-20
|
-25
|
-30
|
-35
|
-40
|
-45
|
-50
|
-55
|
-60
|
0
|
0
|
4
|
7
|
12
|
16
|
23
|
29
|
33
|
38
|
45
|
54
|
62
|
70
|
15
|
0
|
3
|
5
|
9
|
12
|
17
|
21
|
26
|
32
|
40
|
52
|
64
|
81
|
25
|
0
|
1
|
3
|
6
|
9
|
10
|
13
|
18
|
27
|
39
|
58
|
79
|
94
|
35
|
0
|
0
|
1
|
2
|
4
|
7
|
10
|
15
|
24
|
43
|
61
|
85
|
111
|
Table 9
The CCPF value of the ZZ1 during shaking at the specific shaking times under 4D working condition
shaking time(s)
|
Longitudinal depth of pile(cm)
|
0
|
-5
|
-10
|
-15
|
-20
|
-25
|
-30
|
-35
|
-40
|
-45
|
-50
|
-55
|
-60
|
0
|
0
|
3
|
6
|
10
|
15
|
20
|
26
|
31
|
38
|
43
|
51
|
58
|
65
|
15
|
0
|
1
|
2
|
4
|
8
|
12
|
17
|
24
|
31
|
42
|
53
|
64
|
78
|
25
|
0
|
0
|
1
|
3
|
5
|
7
|
10
|
14
|
18
|
25
|
43
|
64
|
89
|
35
|
0
|
0
|
0
|
2
|
3
|
5
|
7
|
9
|
14
|
20
|
34
|
61
|
94
|
Table 10
The CCPF value of the ZZ1 during shaking at the specific shaking times under 5D working condition
shaking time(s)
|
Longitudinal depth of pile(cm)
|
0
|
-5
|
-10
|
-15
|
-20
|
-25
|
-30
|
-35
|
-40
|
-45
|
-50
|
-55
|
-60
|
0
|
0
|
2
|
5
|
10
|
15
|
20
|
26
|
31
|
38
|
43
|
50
|
57
|
63
|
15
|
0
|
1
|
2
|
4
|
8
|
12
|
17
|
24
|
31
|
42
|
53
|
64
|
79
|
25
|
0
|
0
|
1
|
2
|
5
|
7
|
10
|
15
|
20
|
29
|
42
|
63
|
90
|
35
|
0
|
0
|
0
|
1
|
3
|
7
|
11
|
15
|
18
|
24
|
33
|
58
|
92
|
Table 11
The CCPF value of the ZZ1 during shaking at the specific shaking times under 6D working condition
shaking time(s)
|
Longitudinal depth of pile(cm)
|
0
|
-5
|
-10
|
-15
|
-20
|
-25
|
-30
|
-35
|
-40
|
-45
|
-50
|
-55
|
-60
|
0
|
0
|
2
|
4
|
9
|
14
|
19
|
25
|
30
|
37
|
44
|
51
|
57
|
62
|
15
|
0
|
1
|
2
|
4
|
8
|
11
|
15
|
22
|
29
|
40
|
50
|
64
|
75
|
25
|
0
|
0
|
1
|
2
|
5
|
7
|
12
|
15
|
20
|
29
|
42
|
63
|
86
|
35
|
0
|
0
|
0
|
1
|
3
|
7
|
10
|
16
|
19
|
25
|
35
|
59
|
92
|
By analyzing 3D working conditions, the CCPF value at the same position of pile body decreases gradually with the extension of vibration time in the range of 0 to -50cm and increases gradually in the range of -50cm to -60cm. The distribution curve of CCPF at each moment intersects at -40 ~ 50cm of the pile body, and the maximum value of CCPF occurs at the bottom of the pile at each moment of vibration. From 0.75 at 0s to 1.28 at 35s, and the maximum CCPF of 0s and 15s is less than 1. Based on previous research [14], no liquefaction occurs in soil around the pile before 20s of vibration, which indicates that the actual load on the top of ZZ1 pile is less than the average of the total load. After 20 seconds of vibration, the soil begins to liquefy, which is approximately equal to 1 at 25 seconds, indicating that the load on the top of the pile is approximately equal to the average of the total load. More than 1 at 35S indicates that with the continuous liquefaction of soil from top to bottom, the bearing load of soil between piles decreases gradually due to group pile effect, and the bearing load of each foundation pile increases accordingly, which indicates that the bearing load on top of ZZ1 pile is greater than the average of total load.
Under 3.5D working conditions, the change curves of CCPF values at different times of vibration are similar. According to the analysis of 3D working condition, only when the vibration is 35s, the load on the top of the pile is greater than the average value, and other times are less than the average value. From the CCPF distribution curve, it can be seen that the intersection point moves down a little along the pile body compared with the 3D condition, about − 50cm.
The distribution characteristics of CCPF curves under 4D, 5D and 6D conditions are the same. At each vibration moment, the value of CCPF at the bottom of pile is less than 1, which means that the load at the top of pile is less than the average value of the total load at each time. The steepness of CCPF curve reflects the change degree of friction resistance along the side of the pile body at each moment of vibration. Because the actual load on the pile top varies with the liquefaction degree at each moment of vibration, the CCPF value can not reflect the friction resistance on the side of the pile at each time and there is no comparability. The intersection points are all concentrated at -50cm, which continues to decline compared with 3.5D conditions.
The variation curve of CCPF at the bottom of middle pile (ZZ1) in pile group foundation with vibration time is shown in Fig. 11. The relevant data see the Table 12.
Table 12
The CCPF at the bottom of ZZ1 during shaking under different working conditions
different time
|
Pile spacing(D)
|
3
|
3.5
|
4
|
5
|
6
|
0s
|
75
|
70
|
65
|
63
|
64
|
15s
|
86
|
81
|
78
|
79
|
78.5
|
25s
|
100
|
94
|
89
|
90
|
87.8
|
35s
|
118
|
111
|
94
|
92
|
91.5
|
Figure 11 shows that under certain pile spacing, the value of CCPF gradually increases with the duration of vibration, which indicates that the actual load on the top of ZZ1 pile increases with the increase of vibration time. The same vibration time of different spacing between piles decreases with the increase of spacing between piles, which indicates that the actual load on the top of piles decreases with the increase of spacing between piles.