3.1. Survey questionnaire
Out of the fifty-three, only thirty-one participated and completed the questionnaire, indicating a response rate of 59%. initially, the findings show no significant differences in terms of participants demographics such as gender, position and involvement in the implementation project. Table 1 shows the percentage of male and female participation in the survey. It is evident that participation was male dominant, with 80.6% of participants being male. Female participation was found to be only 16.1%. This reflects the actual proportion of females and males in the Saudi MoH, where the majority of the staff are male. As seen in Table 1 more than have of the participants recorded their involvement in previous EHRS implementation project. The participants in the survey were found to be from diverse professional roles. The assistants formed the highest number of participants, at twenty-one (67.7%). Only one deputy manager participated in this study, and three participants from other positions. Finally, out of thirty-one participants, twenty (64.5%) declared that they were directly involved in the process of implementation and five (16.1%) declared that they aided the process through an indirect connection. Six (19.4%) participants did not declare the nature of their involvement.
Table 1
Participant distribution based on gender, previous involvement in EHRS implementation projects, position, and role in the implementation project
Gender
|
Male
|
25
|
80.6
|
Female
|
5
|
16.1
|
Missing
|
1
|
3.3
|
Total
|
31
|
100
|
Previous involvement in EHRS implementation projects
|
YES
|
18
|
58.1
|
NO
|
13
|
41.9
|
Total
|
31
|
100.0
|
position
|
General Manager
|
3
|
9.7
|
Deputy Manager
|
1
|
3.2
|
Head of Department
|
3
|
9.7
|
Deputy Head of Department
|
3
|
9.7
|
Assistant
|
21
|
67.7
|
Total
|
31
|
100.0
|
Role in the implementation project
|
Direct
|
20
|
64.5
|
Indirect
|
5
|
16.1
|
Total
|
25
|
80.6
|
The impact of CPM was explored with nine items Table 2 illustrates the impact of CPM on EHRS implementation. Overall, there was an extremely high agreement on all items (above 90%), with median scores being six or seven. Item 1) “Overall impact is positive”, showed an agreement of 96.8% and a median score of seven, where participants strongly agree that CPM positively influences EHRS implementation in PHCs in SA. Whereas the lowest rank was given to item 9) “Improve project team communication” (90.4%), which is also considered very high with median score of six.
Table 2
Participant responses to items representing the impact of CPM on EHRS implementation in PHCs
Items
|
Strongly disagree
|
Disagree
|
Somewhat disagree
|
No opinion
|
Somewhat agree
|
Agree
|
Strongly agree
|
Median
|
Total agreement
|
Rank
|
Overall impact is positive
|
N
|
|
|
|
1
|
|
5
|
25
|
7
|
30
|
1
|
%
|
|
|
|
3.2
|
|
16.1
|
80.6
|
96.8
|
Improve systems integration and interoperability
|
N
|
|
|
|
1
|
|
12
|
18
|
7
|
30
|
2
|
%
|
|
|
|
3.2
|
|
38.7
|
58.1
|
96.8
|
Better software selection
|
N
|
|
1
|
|
1
|
1
|
7
|
21
|
7
|
29
|
3
|
%
|
|
3.2
|
|
3.2
|
3.2
|
22.6
|
67.7
|
93.5
|
Easier to manage EHRS implementation in a large number of PHCs that are widely dispersed
|
N
|
|
|
1
|
1
|
|
12
|
17
|
7
|
29
|
4
|
%
|
|
|
3.2
|
3.2
|
|
38.7
|
54.8
|
93.5
|
Better project team selection
|
N
|
|
|
|
2
|
4
|
8
|
17
|
7
|
29
|
5
|
%
|
|
|
|
6.5
|
12.9
|
25.8
|
54.8
|
93.5
|
Better decision-making
|
N
|
|
1
|
|
2
|
|
6
|
22
|
7
|
28
|
6
|
%
|
|
3.2
|
|
6.5
|
|
19.4
|
71.0
|
90.4
|
Improve implementation of the strategic plan
|
N
|
|
1
|
|
2
|
1
|
9
|
18
|
7
|
28
|
7
|
%
|
|
3.2
|
|
6.5
|
3.2
|
29.0
|
58.1
|
90.4
|
Help leading and managing the project
|
N
|
|
|
1
|
1
|
3
|
10
|
15
|
6.50
|
28
|
8
|
%
|
|
|
3.2
|
3.2
|
9.7
|
32.3
|
48.4
|
90.4
|
Improve project team communication
|
N
|
|
|
|
3
|
1
|
18
|
9
|
6
|
28
|
9
|
%
|
|
|
|
9.7
|
3.2
|
58.1
|
29.0
|
90.4
|
3.2. Semi-structured interviews
The authors invited fifty-three members of project team to participate in the semi-structure interviews. However, only 14 participants accepted to participate in the semi-structured interviews. The project team members who accepted to participate in this study categorised into five different roles. Three of them were General managers (GM), one Software Developer (SD), three Head of Department (HD), two Deputy Head of Department (DHD) and five Data Analyst (DA).
As mentioned previously we analyzed all transcripts by the semi-structured interview using N-Vivo software which generated seven main themes and thirty-two codes. The findings showed a consensus that CPM had a positive impact on the implementation of EHRS in PHCs in SA. Some of the project team emphasised that CPM was best suited to the nature of the management system in Saudi Arabia. Some of the participants stated that this type of management system was appropriate in SA due to the similarities of the functions and business processes in the PHCs. It was commented by some those decisions related to EHRS implementation should be made centrally by the Saudi MoH to enhance the success of the project.
“…particularly in SA, because the PHCs in SA are similar, are under the Ministry's management and all have the same functions.” (DA 2)
“In the SA, in particular, it is necessary to use CPM to ensure project success.” (SD 1)
However, others suggested that the utilisation of a semi-centralised project management system is more effective for implementing a large-scale EHRS. They argued that the adoption of this type of management represented a major challenge to the Saudi MoH and would be more effective if the MoH involved representatives from regional sub-departments in decision-making. So, decisions regarding EHRS implementation could be made in coordination with representatives from lower levels, such as health affairs’ administrators in the regions or members of the PHCs.
“CPM is a challenge for the Ministry represented by the IT department due to the scale of the project, and therefore must involve sub-departments, health affairs in regions and also PHCs.” (HD 2)
The impact of CPM on decision-making
All participants agreed that CPM has a positive impact on decision-making. For example:
“CPM’s role is very positive to handle large-scale projects while making significant decisions such as selecting the type of EHRS. In addition, CPM can reduce planning and implementation time for large-scale projects.” (GM 1)
“CPM has a very positive impact on decision-making.” (DA 3)
3.4. The impact of CPM on geographical challenges
The geographical nature of SA is considered a challenge that may affect the success of EHRS implementation.
“Geographical nature of SA was a challenge to the MoH. Therefore, CPM assists the project team” (HD2)
Nevertheless, there was some disagreement; the head of the department thought that CPM has a negative impact on geographical factors.
“I think the effect is negative. Because CPM limited the involvement of other members from different regions in SA who could give better insight about their regions, especially geographical challenges” (HD3)
On the other hand, one of the DAs believed that CPM had no impact on geographical factors.
“CPM have no impact on this aspect where geographic challenges consider as technological which then can be overcome by developing appropriate infrastructure.” (DA 2)
The impact of CPM on EHRS interoperability
Interoperability was another measured factor found to be positively influenced by CPM. CPM facilitates communication among project teams to unify decision-making regarding a system that can be interoperable in the future. In addition, this contributes to making the process of communication between the systems more efficient and smoother, and minimises any issues related to future EHRS interoperability. Consequently, this matter will reflect positively on EHRS implementation.
“EHRS interoperability is crucial, it is highly affected by CPM and cannot succeed unless CPM is adopted especially in large-scale projects where different systems may selected and then implemented. We considered interoperable EHRS because the decision related to the interoperability and data exchange was made by one project team at the headquarter of the Saudi MOH. Therefore, communication among the project team was easy and effective for this purpose. So, it has a very positive impact.” (HD1)
The impact of CPM on the scale of the EHRS implementation project
There was agreement on the positive impact of CPM in overcoming challenges related to scale of the project. A general manager believed that the CPM was “Certainly positive” (GM1). Other participants stated, for example:
“Implementing EHRS in very large number of PHCs which exceeded 2000 is not an easy mission due to the complexity of any project related to the IT. If all decisions and procedures related to project will not be made centrally by one project team, many challenges and conflicts may raise, and the project may fail. So defiantly CPM has a very positive effect.” (HD 3)
“The CPM system has a positive effect regarding the implementation of the EHRS in a large number of centres.” (SD 1)
Firmly believing that CPM had a positive impact on the number of PHCs, a proposal was made to divide the PHCs into zones or regions to overcome any issues related to the scale of the project and facilitate the implementation process.
“It has a positive impact. I would probably recommend dividing them into groups of different regions or zones.” (DA 3)
The impact of CPM on planning EHRS implementation in PHCs in SA
The majority of the project team agreed that CPM had a positive impact on planning for the implementation of an EHRS. For instance, DA 1 said CPM had a “very positive effect”, and GM3 stated that the impact of CPM was “positive”. One of the general managers illustrated that CPM helped to avoid many of the technical and administrative problems that occurred during the planning phase by standardising any decisions and opinions. In addition, CPM helped to reduce the costs of the project, since the planning occurreed centrally at the Saudi MoH.
“It is better to be centralised, because when the planning and entire implementiaon process is centralised the cost and time of the project will be reduced.” (GM2)
On the other hand, one of the DAs believed that CPM had a negative impact on EHRS implementation planning.
“The CPM has negative impact on the planning phase due to the limited involvement of other parties and stakeholders such as members of PHCs or patients” (DA 3)
3.8. The impact of CPM on software selection
According to the participants’ responses, CPM had a positive impact on the software selection process. As illustrated by one of the general managers, “CPM is very positive, without a doubt” (GM1). In this context, software selection should be carried out centrally and under the supervision of the Saudi MoH.
“Such a decision regarding the software selection should be centralised at the top management of the Ministry to avoid any compatibility issue especially for large-scale project where multiple software may implement.” (HD 2)
Likewise, one of the heads of department emphasised the importance of software selection being made centrally at the top level of the Saudi MoH. He believed that lower-level organisations such as regional health affairs do not have the ability to select or even examine an EHRS due to a lack of IT expertise.
“Before choosing a system, we must evaluate and review the EHRS and compare prices, system usability, system efficiency, etc. These things cannot be done in health centres where there are no experts in IT.” (HD 3)
On the other hand, due to previous experience in similar EHRS implementation projects, one of the DAs claims to have adopted the concept of a semi-centralised project management to enhance software selection.
“From the experience of previous implementation projects, there were many notes from regions about the system, so health affairs in the regions should participate in system selection.” (DA 2)
The impact of CPM on team communication processes
There was consensus that CPM had a positive impact on team communication. For instance, HD 2 said “CPM has very positive effect on communications among project team”. As illustrated by some of the participants, project team communications were made at the headquarter in the Saudi MoH in the form of meetings and workshops. All such meetings and workshops also involved the project team at different departments and different regions. This greatly facilitated and accelerated the decision-making process.
“…CPM is better to ensure faster and more effective communication between the project team.” (DA 2).
However, others thought that CPM had no influence on the communications among project team.
“…due to the development of telecommunications and all other media meetings and other form of communication can be made from distance and all stakeholders can be involved remotely via SKYPE or video conferences.” (GM 1).
The impact of CPM on project team selection
Team selection was also positively affected by CPM. according to one of the general managers, team selection was easier and more efficient when conducted centrally by the Saudi MoH. According to GM2, “CPM is the best” in terms of enhancing project selection, and DHD1 said, “It has a very positive impact”.
“…CPM dramatically facilitates this process because project team selection is easier and of more effective.” (GM 1)