The research sites information and analysis are collected off information from Report No. FHWA/OH-2021-04 Division of Engineering Research on Call Agreement 31796 Task 7 – Service Evaluation of Highway Structures with Soil-Bearing Spread Footings [25]. This section presents background information/data for four sites (MAH-680-2.83, CUY-77-14.35, FAI-33-13.09, and CUY/SUM-271-00.00/14.87), where spread footings were monitored during different phases of construction and surveyed between October 13 and 14, 2020.
MAH-680-2.83 Bridge
This is a four-span bridge (MAH-680-0283) carrying Vestal Road (Rd) over Interstate 680 (IR-680) in Mahoning County in northwestern Youngstown, Ohio. In 2016 rehabilitation work was performed for the bridge. The work removed the existing superstructure and three piers and raised the existing abutment seats. Therefore, new spread footings were constructed for the piers only. Existing spread footings at the abutments were used. The bridge is four-span continuous painted steel girders with reinforced concrete deck on new semi-integral abutments, new bearings, and new cap and column piers founded on spread footings. The footing width for Piers 1 and 3 is 4.4 m, while the footing width is 2.74 m for Pier 2.
Site stratigraphy consists of hard silt and clay (A-4) near the ground surface to an elevation of about 284 m, where a dense sand and gravel or sand layer (A-1-b, A-3) 1.5 to 4.5 m thick was encountered. Below was another hard layer of silt/ sand mixture (A-4) and a hard silt layer beneath it. Groundwater was not encountered. The bottom footing elevations for piers 1,2, and 3 are 286.5 m, 286.2 m, and 285.6 m, respectively. The average SPT N value stayed relatively constant, around 50 below the foundation depth for all substructures.
On October 6, 2020, a site visit was performed to the MAH-680-0283 bridge. The bridge deck and sidewalk were inspected for cracking and settlements; however, no indications of settlements or cracking were found. Piers were found to be in good condition; no settlement was observed. One of the PVC pipes over the settlement pins was observed to be broken off at the groundline. The existing bridge foundation was founded on spread footing functions as designed, and no signs of any settlements. Figure 1. shows a picture of the MAH-680-0283 bridge.
Recently, multiple pier footings were surveyed. Piers spread footings were monitored after pouring the footings' concrete, before and after beam placement, after pouring the deck's concrete, and after project completion. Table 1 presents the recorded monitoring data for the right and left monuments of each pier.
Table 1
MAH-680-2.83 Footings Settlement Monitoring Data
Stage | Elevation of Left Monument (m) | Elevation of Right Monument (m) | Date |
Pier 1 | Pier 2 | Pier 3 | Pier 1 | Pier 2 | Pier 3 |
After Footings Poured | 287.722 | 287.497 | 286.808 | 287.707 | 287.466 | 286.762 | 2016-05-31 |
Before Beams | 287.710 | 287.487 | 286.808 | 287.704 | 287.466 | 286.762 | 2016-06-28 |
After Beams | 287.707 | 287.484 | 286.805 | 287.707 | 287.463 | 286.759 | 2016-07-28 |
After Deck Pour | 287.710 | 287.487 | 286.808 | 287.713 | 287.466 | 286.765 | 2016-10-05 |
Project Completion | 287.710 | 287.484 | 286.805 | 287.707 | 287.466 | 286.765 | 2016-11-12 |
This Task | 287.710 | 287.478 | 286.811 | 287.713 | 287.469 | 286.768 | 2020-10-13 |
Measured Sett. at Project Completion (mm) | 12.00 | 13.00 | 3.00 | 0.000 | 0.000 | -3.00 | |
Measured Settlements under this Task (mm) | 12.00 | 19.00 | -3.00 | -6.00 | -3.00 | -6.00 | |
At project completion, the maximum measured settlement is about 13 mm. Recently, the final maximum measured settlement is about 19 mm. It should be noted that the minus values appear due to elevation reading tolerable error and refer to no settlement. After approximately four years, settlements did not change significantly. The settlement was within tolerable limits for these span lengths. The measured settlement to girder length ratio was 0.00067. This is well below the acceptable limit of 0.004, as documented by Felix Yokel (26).
The measured settlement was negative for some of the substructure units. The negative settlement can result from either settlement of the benchmark used or measurement error, as the surveying accuracy is to the nearest 3.175 mm.
CUY-77-14.35 Walls
The project consists of four cast-in-place (CIP) concrete cantilever walls (Walls 1,2,3 and 4) and a bridge replacement for Bridge No. CUY-1433 L&R over I.R. 490 and Ramps, south of Cleveland, Ohio. The bridge is a three-span continuous steel hybrid girder composite with a reinforced concrete deck on reinforced concrete piers and semi-integral abutments. The bridge is supported on 406 mm of cast-in-place reinforced concrete piles. Settlements were monitored for walls 1 and 4, the left rear abutment wing wall (Wall 2), and the right forward abutment wing wall (Wall 3).
The footing width for walls 1 and 4 is 3.8 m and 3 m, respectively. The footing width for walls 2 and 3 is 4.26 m.
On October 6, 2020, a site visit was performed. The cantilevered cast-in-place concrete wing walls were inspected and found to be plumb vertically; no leaning or sliding of the walls was observed. The existing bridge retaining walls foundation founded on spread footing is functioning as designed. Figure 2 shows the Right Forward Abutment Wing Wall (Wall 3).
CUY-77-14.35 Soil Profile
Wall 1 (I.R. 77 Sta. 72 + 19.25 to Sta. 74 + 20.54)
Fill was encountered below the pavement to a depth of 7.77 m and consisted of medium-dense to hard sandy silt (A-4) and dense coarse and fine sand (A-3). Natural soils were encountered below the fill to the termination depth of 12.2 m and consisted of medium dense, fine sand (A-3). Groundwater seepage was not encountered. The average SPT N value ranged from 23 to 46 under the wall footing.
Wall 4 (I.R. 77 Sta. 80 + 34.56 to Sta. 82 + 71.00)
Fill was encountered below the pavement to a depth of 7 m and consisted of medium-dense sandy silt (A-4) and dense gravel with sand (A-1-b). Natural soils were encountered below the fill to the termination depth of 12.2 m and consisted of soft to medium-stiff silt and clay (A-6), medium-dense to dense coarse and fine sand (A-3), and dense, fine sand (A-3). No groundwater seepage was encountered. The average SPT N value ranged from 15 to 45 under the wall footing.
Bridge No. CUY-1433 L&R over I.R. 490 and Ramps Wing Walls
Left Rear Abutment wing wall-Boring BB-106 (Wall 2)
Material visually identified as fill was encountered below the pavement to a depth of 9.75 m and consisted of medium-dense to very-dense gravel with sand (A-1-b) and dense coarse and fine sand (A-3). Natural soils were encountered below the fill to the termination depth of 27.4 m and consisted of medium-dense fine sand (A-3), medium-dense to very-dense coarse and fine sand (A-3), stiff to very-stiff silt (A-4), and medium-stiff to stiff silty-clay (A-6). Groundwater seepage was encountered at a depth of 16.3 m, and groundwater was encountered at a depth of 17.8 m. The average SPT N value ranged from 15 to 44 under the wall footing.
Right forward abutment wing wall (Wall 3)
Material visually identified as fill was encountered below the pavement to a depth of 9.75 m and consisted of dense sandy silt (A-4), dense silt (A-4), and medium-dense fine sand (A-3), and dense to very-dense coarse and fine sand (A-3). Natural soils were encountered below the fill to the termination depth of 27.4 m and consisted of medium-dense to very-dense fine sand (A-3), medium-stiff to dense sandy silt (A-4), and dense silt (A-4). Groundwater seepage was encountered at a depth of 17.8 m, and water was measured at a depth of 20.9 m at the completion of the drilling. The average SPT N value ranged from 14 to 41 under the wall footing.
CUY-77-14.35 Settlement Monitoring Data
Spread footings were monitored after pouring the footings' concrete and after project completion. Recently, footings were surveyed. Table 2 presents the recorded monitoring data for the monuments of the left rear abutment wing wall (Wall 2) and the right forward abutment wing wall (Wall 3). At project completion, the measured settlements are about 6.0 mm for Wall 2 and Wall 3. Recently, the maximum measured settlement is about 37 mm and 18 mm for Wall 2 and Wall 3, respectively. It should be noted that settlements did not change significantly except for Wall 2, monument 2.
Table 2
Bridge No. CUY-77-1433 Wing Walls Settlement Monitoring Data
Stage | Elevation (m) | Date |
Left Rear Abutment Wing Wall (Wall 2) | Right Forward Abutment Wing Wall (Wall 3) |
Monument-1 | Monument-2 | Monument-1 | Monument-2 |
22 + 91.63,19 m LT | 22 + 74.98,19 m LT | 24 + 19.2, 19 m RT | 24 + 34.64, 19 m RT |
After Footing Concrete Placed | 205.325 | 205.338 | 207.380 | 207.383 | N. A |
Project Completion | 205.319 | 205.332 | 207.374 | 207.377 | N. A |
Recent, this Task | 205.319 | 205.301 | 207.362 | 207.368 | 2020-10-13 |
Measured Sett. at Project Completion (mm) | 6.00 | 6.00 | 6.00 | 6.00 | |
Measured Settlements under this Task (mm) | 6.00 | 37.00 | 18.00 | 15.00 | |
Table 3 presents the recorded monitoring data for the monuments of Walls 1 and 4. At project completion, the maximum measured settlement is about 3 mm for Wall 1 and Wall 4. Recently, the measured settlements ranged from 3 to 6 mm for Wall 1 and from 125 to 195 mm for Wall 4. Settlements did not change significantly for Wall 1. However, Wall 4 experienced excessive settlements due to the existing 0.5 to 1.0 m layer of soft to medium-stiff silt and clay (A-6), which was encountered immediately beneath the fill material at the elevation of 203 m. This layer is located 3.25 m below the bottom of Wall 4 footing. The wall was inspected and found to be plumb vertically; no leaning or sliding of the walls was observed. Therefore, the benchmark may have a problem.
Table 3
Walls 1 and 4 Settlement Monitoring Data
Stage | Elevation (m) | Date |
Wall 1 | Wall 4 |
Monument-1 | Monument-2 | Monument-1 | Monument-2 |
22 + 32.81, 19.5 m RT | 22 + 60.96, 19.8 m RT | 24 + 49.72, 18.9 m LT | 24 + 94.64, 18.9 m LT |
After Footing Concrete Placed | 205.502 | 205.490 | 207.121 | 207.651 | N. A |
Project Completion | 205.505 | 205.490 | 207.118 | 207.651 | N. A |
Recent, this Task | 205.499 | 205.484 | 206.996 | 207.456 | 2020-10-13 |
Measured Sett. at Project Completion (mm) | -3.00 | 0.000 | 3.00 | 0.000 | |
Measured Settlements under this Task (mm) | 3.00 | 6.00 | 125.00 | 195.00 | |
FAI-33-13.09 Bridge
This is a four-span bridge (FAI-33-1309) carrying Delmont Road over U.S. Route 33 (Lancaster Bypass) west of Lancaster in Fairfield County, Ohio. The bridge is a four-Span continuous composite steel girder bridge with semi-integral type abutments and cap and columns type piers on spread footings. The footing width is 2.4 m for the rear and forward abutment. The footing width is 4.25 m for all piers.
On October 5, 2020, a site visit was performed to the FAI-33-1309 bridge. The team inspected the embankment slopes, roadway settlement at abutments, concrete deck, and relative substructure orientation. The team found no evidence of settlements. The soils around the piers were found to be soft, but this was due to drainage. Some of the PVC caps were missing or damaged due to vandalism. The existing bridge foundations founded on spread footing are functioning as designed. Figure 3. shows the FAI-33-1390 bridge.
Field exploration was performed using five boreholes per the original geotechnical report. Each one of the five borings first encountered between 0.1 and 0.3 m of topsoil. Underlying the topsoil, the five borings typically encountered cohesive soils consisting of stiff to hard silt and clay (A-6) and silty clay (A-6) to depths of between 3.2 and 6.25 m. Some of these soils were organic in nature. Underlying these cohesive soils, each of the five borings generally encountered medium dense to very dense non-cohesive soils, including gravel with sand (A-1-b), gravel with sand and silt (A-2-4), fine sand (A-3), and coarse and fine sand (A-3). These soils were encountered to the completion depths of the borings in boring B-33 and B-34 and were encountered to depths of between 15 and 19 m in borings B-30, B-31, and B-32, where bedrock was encountered. It should be noted that material classified as silt (A-4) was encountered in boring B-34. However, this material was encountered at depths greater than 15 m. Bedrock was encountered in borings B-30, B-31, and B-32 at depths of between 15 and 19 m. The bedrock consisted of medium-hard broken
sandstone with RQDs of between 30% and 50%. Water seepage was encountered at depths of between 2 and 5 m. The average SPT N value ranged from 12 to 50 below the foundation depth for all substructures.
Spread footings were monitored after pouring the footings' concrete, before and after beams placement, after pouring the deck's concrete, and after project completion. Recently, footings were surveyed. Table 4 presents the recorded monitoring data for the right and left monuments of each pier. At project completion, the measured settlements ranged from 9 mm to 30 mm. Recently, the final measured settlements ranged from 3 to 64 mm. After approximately 19 years, settlements did not change significantly except for the rear abutment. It should be noted that monuments could not be located at the right rear abutment, left and right pier 3. As at these locations, survey monument information was not available; the survey crew established temporary benchmarks, which were tied into two ODOT benchmarks via GPS observations.
Table 4
FAI-33-13.09 Footings Settlement Monitoring Data
Stage | Elevation of Left Monument (m) | Elevation of Right Monument (m) | Date |
Rear Abut. | Pier 1 | Pier 2 | Pier 3 | F.R. Abut. | Rear Abut. | Pier 1 | Pier 2 | Pier 3 | F.R. Abut. |
After Footings Poured | 278.929 | 274.143 | 274.738 | 273.601 | 279.145 | 278.956 | 274.165 | 274.744 | 273.656 | 279.163 | Between 06 − 05 and 07-12-2001 |
Before Beams | 278.929 | 274.143 | 274.735 | 273.601 | 279.139 | 278.956 | 274.165 | 274.744 | 273.656 | 279.157 | 2001-10-19 |
After Beams | 278.901 | 274.137 | 274.735 | 273.598 | 279.130 | 278.938 | 274.158 | 274.741 | 273.649 | 279.148 | 2002-03-21 |
After Deck Pour | 278.910 | 274.131 | 274.731 | 273.595 | 279.136 | 278.932 | 274.152 | 274.735 | 273.646 | 279.154 | 2002-04-26 |
Project Completion | 278.904 | 274.131 | 274.728 | 273.592 | 279.133 | 278.926 | N. Aa | 274.735 | 273.646 | 279.151 | 2002-08-05 |
Recent, this Task | 278.865 | 274.146 | 274.735 | 273.741 | 279.121 | 279.063 | 274.155 | 274.738 | 273.835 | 279.145 | 2020-10-14 |
Measured Sett. at Project Completion (mm) | 25.00 | 12.00 | 10.00 | 9.00 | 12.00 | 30.00 | N. Aa | 9.00 | 10.00 | 12.00 | |
Measured Settlements under this Task (mm) | 64.00 | -3.00 | 3.00 | -140b | 24.00 | -107b | 10.00 | 6.00 | -179b | 18.00 | |
a Not Available, b Monuments could not be located.
CUY/SUM-271-00.00/14.87
The CUY/SUM-271-00.00/14.87 and CUY/SUM-480-29.58/00.00 project calls for the design and construction of three (3) new retaining walls identified as RW-1 (WS1), RW-2 (SW1), and RW-3 (WS2) in Summit/Cuyahoga Counties, Ohio. These retaining walls were constructed in association with constructing two additional Lanes identified as S-W and W-S located along the outside shoulders of IR-271 SB and N.B. between the Summit County Line and Alexander Road, south of Cleveland, Ohio. Settlements were monitored for RW-1 (WS1).
On October 6, 2020, a site visit was performed by E.L. Robinson Engineering. The cantilevered cast-in-place concrete wall was inspected and found to be plumb vertically; no leaning or sliding of the walls was observed. The existing retaining wall foundation founded on spread footing is functioning as designed. Figure 4 shows RW-1 (WS1).
Field exploration was performed using two boreholes per the original geotechnical report. The subsurface soils encountered in both test borings were predominantly cohesive in nature and consisted of both fill materials and natural soils. The fill materials located above the natural soils consisted of silt and clay (A-6) and silty clay (A-6). The fill material's approximate thickness was 2.5 m in boring test B-007-1-13 and one meter in boring test B-007-4-13. Natural soils encountered above bedrock in boring test B-007-4-13 and to the termination depth in boring test B-007-1-13 consisted of sandy silt (A-4), silt, and clay (A-6), non-plastic sandy silt (A-4), and coarse and fine sand (A-3). Bedrock consisting of gray, severely to highly weathered shale was encountered at an approximate depth of 18 m in boring test B-007-4-13. The consistency of the cohesive soils ranged from "medium stiff" to "hard" but was generally "very stiff.” The relative density of the non-cohesive soils ranged from "dense" to "very dense."
Table 5 presents the recorded monitoring data for RW-1 (WS1). Settlements were not collected for this recently constructed wall. At project completion, the wall did not experience any settlements based on the provided data.
Table 5
RW-1 (WS1) Settlement Monitoring Data
Stage | Elevation (m) | Date |
Sta. 988 + 69.80 | Sta. 988 + 91.3 | Sta. 989 + 16.69 | Sta. 989 + 33.60 | Sta. 989 + 50.51 | Sta. 989 + 75.88 |
After Footing Concrete is Placed | 316.550 | 316.527 | 316.550 | 316.536 | 316.530 | 316.379 | 1/8/2019 |
After Wall Concrete is Placed and backfilled | 316.550 | 316.527 | 316.550 | 316.536 | 316.530 | 316.379 | 7/26/2019 |
Project Completion | 316.550 | 316.527 | 316.550 | 316.536 | 316.530 | 316.379 | 10/30/2019 |
Recent, this Task | N. Aa | N. Aa | N. Aa | N. Aa | N. Aa | N. Aa | |
Measured Sett. at Project Completion (mm) | N.A. | N.A. | N.A. | N.A. | N.A. | N.A. | |
Measured Settlements under this Task (mm) | N. Aa | N. Aa | N. Aa | N. Aa | N. Aa | N. Aa | |
a Not Available, settlements data were not collected under this task |
It should be noted that consolidation settlement calculations require soil parameters that are not included in the provided soil reports. The only soil report that provided such information is CUY/SUM 271-00.00/14.87 RW-1. Therefore, the estimated settlement for this wall is the total settlement.
Comparison Between Estimated and Measured Settlements
In this section, a comparison is made between the estimated and measured settlements. Measured settlements are presented in the previous sections of this report. Hough (10) is used to estimate the settlements of spread footing on cohesionless soil as specified in section 10.6.2.4 of the AASHTO LRFD Bridge Design Specifications.
Spread footing settlements should be estimated using computational methods based on laboratory or in-situ testing results or both. The soil parameters used in the computations should be chosen to reflect the loading history of the ground, the construction sequence, and the effects of soil layering.
Settlements of cohesionless soil can be estimated using Hough’s (10) method as explained in Equations 1 and 2. Generally, conservative settlement estimates may be obtained using the elastic half-space procedure or the empirical method by Hough (10). The Hough method has several advantages over other methods used to estimate settlement in cohesionless soil deposits, including express consideration of soil layering and the zone of stress influence beneath a footing of finite size. The subsurface soil profile should be subdivided into layers based on stratigraphy to a depth of about three times the footing width. The maximum layer thickness should be about 3 m.
$${\text{S}}_{e}={\sum }_{i=1}^{n}\varDelta {\text{H}}_{i}$$
1
$$\varDelta {\text{H}}_{i}={\text{H}}_{c}\frac{1}{{C}^{{\prime }}}\text{l}\text{o}\text{g}\left(\frac{{\sigma }_{o}^{{\prime }}+\varDelta {\sigma }_{v}}{{\sigma }_{o }^{{\prime }}}\right)$$
2
Where:
\(n\) = Number of soil layers within the zone of stress influence of the footing
\(\varDelta {\text{H}}_{i}\) = Elastic settlement of layer i
\({\text{H}}_{c}\) = Initial height of layer i
\({C}^{{\prime }}\) = Bearing Capacity Index, from Fig. 10.6.2.4.2-1 of the AASHTO LRFD Bridge Specifications.
\({\sigma }_{o}^{{\prime }}\) = Initial average effective stress of the subdivided soil layer.
\(\varDelta {\sigma }_{v}\) = Vertical stress increase in the subdivided soil layer due to applied foundation load.
Table 6 presents a comparison between estimated and measured settlements. A comparison is made between the estimated and measured settlements at the end of construction and the recently measured values. It should be noted that average measured settlements were calculated by taking the average of two monuments readings for each footing. The current measured settlements of FAI-33-13.09 pier 3 were ignored because survey monument information was not available.
It can be noted that Hough's method tends to over-predict the immediate settlements (measured at the end of construction). It also over-predicts the current measured settlements for most of the footings. However, Hough's method significantly underpredicts the current measured settlements for some footings where cohesive soil (A-6) layers exist, such as CUY-77-14.35 Wall 4 and the rear abutment of FAI-33-13.09. Therefore, it is important to calculate the long-term settlements when cohesive soils exist.
Table 6
Comparison Between Estimated and Measured Settlements
Project | Structure | Estimated Settlements (mm) | Avg. Measured Settlements (mm) | (Estimated/Measured) Settlement | |
End of Construction | Current Settlement | End of Construction | Current Settlement | |
MAH-680-2.83 | Pier 1 | 17.53 | 6.0 | 3.0 | 2.92 | 5.84 | |
Pier 2 | 12.70 | 6.5 | 8 | 1.95 | 1.59 | |
Pier 3 | 11.94 | 0.0 | -4.5b | N.Aa | N.Aa | |
CUY-77-14.35 | Wall 1 | 17.53 | -1.5b | 4.5 | N.Aa | 3.90 | |
Wall 4 | 13.72 | 1.5 | 160 | 9.14 | 0.09 | |
LT. R.A.Wing Wall (Wall 2) | 22.61 | 6.0 | 21.5 | 3.77 | 1.05 | |
RT. F.A.Wing Wall (Wall 3) | 19.30 | 6 | 16.5 | 3.22 | 1.17 | |
FAI-33-13.09 | Rear Abut. | 23.11 | 27.5 | 64 | 0.84 | 0.36 | |
Pier 1 | 26.16 | 12 | 10 | 2.18 | 2.62 | |
Pier 2 | 33.02 | 9.5 | 4.5 | 3.48 | 7.34 | |
Pier 3 | 26.16 | 9.5 | N.Aa | 2.75 | N.Aa | |
FR. Abut. | 18.54 | 12 | 21 | 1.55 | 0.88 | |
CUY/SUM-271-00.00/14.87 | RW-1 (WS1) | 19.81 | 0.0 | N.Aa | N.Aa | N.Aa | |
a Not Available values |
b negative settlements values, measurement error |
Per the Geotechnical report of CUY/SUM-271-00.00/14.87, the recently constructed Wall RW-1 (WS1) is expected to experience an immediate settlement of 6 mm and consolidation settlements of 13 mm. The wall is expected to experience a total settlement of 20 mm. Consolidation settlements are very important because of the existing cohesive soil below the wall's footing.
Differential Settlements between Substructures
Differential settlements between substructures are presented in Table 7. The table shows differential settlements at the end of construction and the current differential settlements based on a recent survey performed in this study.
MAH-680-0283, at the end of construction, experienced 0.5 mm of differential settlements between piers 1 and 2, also it experienced 6.5 mm between piers 2 and 3. Based on recent settlement monitoring data, the structure experienced 5 mm between piers 1 and 2; and 12.5 mm between piers 2 and 3. It should be noted that those values are within tolerable settlement limits.
Table 7
Differential Settlements between Substructures
Structure No. | Substructure | Ave. Measured Settlements (mm) | Differential Settlements between Substructures (mm) |
End of Construction | Current Settlement | Two Substructures | Based on End of Construction | Based on Current Settlement |
MAH-680-0283 | Pier 1 | 6.0 | 3 | Pier 1 and 2 | 0.5 | 5 |
Pier 2 | 6.5 | 8 | Pier 2 and 3 | 6.5 | 12.5 |
Pier 3 | 0.0 | -4.5 | ---------- | ---------- | ---------- |
FAI-33-1309 | Rear Abut. | 27.5 | 64 | Rear Abut. and Pier 1 | 15.5 | 54 |
Pier 1 | 12 | 10 | Pier 1 and 2 | 2.5 | 5.5 |
Pier 2 | 9.5 | 4.5 | Pier 2 and 3 | 0.0 | N. A |
Pier 3 | 9.5 | N.A | P3 and F.R. Abut. | 2.5 | N. A |
FR. Abut. | 12 | 21 | ---------- | ---------- | ---------- |
FAI-33-1309 experienced tolerable differential settlements of (0.0 to 15.5) mm at the end of construction. However, a recent settlement monitoring survey showed differential settlements of (5.5 to 54) mm, the values at the piers less than those at the end of construction. This may be due to survey issues. It should be noted that differential settlements of 54 mm between the rear abutment and pier 1 is recorded recently because of the 64 mm current settlements at the rear abutment. This may be due to the encountered cohesive soils consisting of stiff to hard silt and clay (A-6) and silty clay (A-6) at deeper layers below the rear abutment. There are no signs of this differential settlement at the rear abutment approach.