4.1 Calculation model
Taking Xinfadi-caoqiao section of Beijing Metro Line 19 as the research background, the calculation model is established. The constitutive model adopts elastic-plastic model and the yield criterion adopts Mohr-Coulomb criterion. The range of stratum simulated by the whole model is 3 ~ 5 times of the tunnel diameter at both ends, about 35 m, and the total width is 70 m; the height of the model is based on the actual overburden thickness, and the buried depth is about 4 m; the tunnel bottom is 36 m, and the total height of the model is 40 m; the total longitudinal length is 70 m. As shown in Fig. 2 The boundary conditions of the model are as follows: the horizontal constraint is imposed on the surrounding boundary, the vertical constraint is imposed on the lower boundary, and the top is a free surface.
4.3 Calculation conditions
The small pilot tunnel excavation and pile construction process are divided into six working conditions for analysis, and the specific excavation methods are as follows:
Working condition 1: first excavate No. ① and No.⑤ small pilot tunnels on both sides, and then excavate No. ③ small pilot tunnel in the middle. After the pilot tunnel is excavated, the pile foundation and crown beam are constructed.
Working condition 2: first excavate No. ① and No. ⑤ small pilot tunnels on both sides, then construct the pile foundation and crown beam of No.① and No. ⑤ small pilot tunnels after excavation, and then excavate No.③ small pilot tunnel in the middle, and construct the pile foundation and crown beam of No. ③small pilot tunnel after excavation.
Working condition 3: first excavate both sides of No. ①small pilot tunnel, and then construct the pile foundation and crown beam of No. ① small pilot tunnel after excavation, then excavate both sides of No. ⑤ small pilot tunnel, and then construct the pile foundation and crown beam of No. ⑤ small pilot tunnel after excavation, finally excavate middle No. ③ small pilot tunnel, and construct the pile foundation and crown beam of No. ③ small pilot tunnel after excavation.
Working condition 4: first excavate the middle No. ③ small pilot tunnel, and then excavate both sides ① and No. ⑤ small pilot tunnels. After the completion of pilot tunnel excavation, pile foundation and crown beam construction are carried out.
Working condition 5: first excavate the middle No. ③small pilot tunnel, and then construct the pile foundation and crown beam of No. ③ small pilot tunnel after excavation, and then excavate both sides No. ① and No. ⑤ small pilot tunnels, and then construct the pile foundation and crown beam of No. ① and No. ⑤ small pilot tunnel after excavation.
Condition 6: first excavate the middle No. ③ small pilot tunnel, then construct the pile foundation and crown beam of No. ③ small pilot tunnel, then excavate both sides No. ① small pilot tunnel, then construct the pile foundation and crown beam of No. ①small pilot tunnel, finally excavate both sides No. ⑤ small pilot tunnel, and then construct the pile foundation and crown beam of No. ⑤ small pilot tunnel.
The design contents of calculation conditions are summarized in Table 2.
Table 2
working condition | Excavation sequence of small pilot tunnel |
1 | ①⑤③②④(Pile driving shall be carried out after the completion of three pilot tunnels) |
2 | ①⑤③②④(Pile driving after completion of small pilot tunnels on both sides) |
3 | ①⑤③②④(Pile immediately after the completion of small pilot tunnel) |
4 | ③①⑤②④(Pile driving shall be carried out after the completion of three pilot tunnels) |
5 | ③①⑤②④(Pile driving after completion of middle pilot tunnel) |
6 | ③①⑤②④(Pile immediately after the completion of small pilot tunnel) |
Note: pile-beam-arch approach (PBA) is adopted. |